The Ultimate “Jump-Start” R12.1 Upgrade Assessment
We do the following in 9 weeks:
Week 1: Technical Upgrade Assessment (2 people)
Week 2: Finish Technical Assessment and Project Plan
Week 3: Functional Assessment (2 people)
-Start the First Pass Upgrade
Week 4: Finish the 1st Pass Upgrade
-Finish the Functional Assessment
Week 5: R12 New Features Training
-Run, Analyze ConfigSnapshot
-Begin Analysis on Custom Objects
Week 6: Perform and document Gap Analysis (3 people)
Week 7: Perform and document Gap Analysis, continued
Week 8: Define Scope and Customizations (2 people)
Week 9: Define Detailed and Customization Schedules (2 people)